FCCPC Seals Meridian Park Estate In Lagos After Buyer Paid N28.5 Million For Duplex And Got Nothing For 6 Years

The Federal Competition and Consumer Protection Commission has sealed the Lagos premises of Meridian Park Estate Ltd after the company failed to deliver a fully paid five-bedroom duplex to a buyer.
The enforcement was carried out by the South-West zonal team of the Commission.

According to reports, the subscriber paid N28.5 million for the property in 2020. Six years later, she had still not received the house. She later reported the matter to the FCCPC for intervention.
Speaking during the enforcement, Marvin Nadah, Deputy Director of Surveillance and Investigation at the FCCPC, said the action followed the refusal of the developer to comply with a directive to hand over the property.
Nadah explained that the Commission started engaging Meridian Park Estate in 2025 after the buyer complained that she had paid in full but had not taken possession.
He said the FCCPC issued a compliance notice to the company in August, giving it one month to deliver the duplex. The Commission said it got no response to the notice.
He added that the enforcement was carried out under Section 150(4)(a) of the Federal Competition and Consumer Protection Act, 2018.
He said the premises will remain sealed until the company complies with the order and directive given to it.
But the Director of Operations of Meridian Park, Uchenna Eze, gave a different account. He said the matter had been resolved and the subscriber had been invited to collect the keys.
Eze said the buyer had paid the required handover fees and the company had scheduled the handover. He added that she said she would send a proxy to collect the keys.
He described the FCCPC action as a surprise, saying the company had received a letter from the Commission earlier in the year and had offered to make copies available.
During the enforcement, the FCCPC South-West Zonal Coordinator, Olubunmi Otti, advised consumers to understand the terms of agreements before paying for goods and services.
She urged property buyers to check delivery arrangements, ensure that important commitments are documented, and deal with reputable vendors.
She said, before you part with your money, collect the product. Let the product be in your hand before you release your money.
Otti also encouraged consumers to report complaints to the Commission instead of keeping quiet, saying such reports help the FCCPC to identify and address violations of consumer rights.
For property buyers, the case shows why it is important to document payment, agreed delivery dates, handover conditions and any additional charges before committing to a purchase.
The Meridian Park case is one of several recent enforcement actions by the FCCPC against real estate developers over undelivered properties.
In November 2026, the Commission sealed Peachville Platinum Estate Limited in Abuja over an alleged failure to deliver a N140 million four-bedroom duplex to a buyer who reportedly paid in full in August 2025.
In April 2026, it also sealed Paradise Estate in Life Camp Extension, Abuja, following complaints from buyers who said they paid for housing units but did not receive them.
In May 2026, the FCCPC sealed Ochacho Group Worldwide and Ti-Bilon over alleged non-compliance with regulatory notices relating to property and refund complaints.
These cases show the range of property-related complaints that have made the Commission to intervene, including delayed delivery, refunds and failure to comply with regulatory directives.
Why do property buyers face delivery delays?
An investigation published in July 2025 documented cases of buyers who paid for residential properties but waited beyond their agreed delivery dates.
One case involved a Nigerian living in the United States who paid about N38 million to N40 million over 18 months for a three-bedroom apartment at Lekki Pride 1 in 2020. The property, initially expected by the end of 2022, was eventually delivered in late 2024. The developer had cited COVID-19 disruptions and rising building material costs for the delay.
Another case involved a N200 million residential building in Lekki, where a developer reportedly requested an additional N50 million one year into a project originally scheduled for completion within 18 months.
Speaking on the issue, registered civil engineer and infrastructure strategist Babatunji Adegoke said some developers make delivery promises without adequate feasibility studies, financing arrangements or professional project management.
Temple Ugwu, Lead Partner and Portfolio Manager at Bluemeen Partners, said even developers who are not fraudulent can run into difficulties when projects depend heavily on subscribers payments instead of adequate internal financing.
The investigation identified financing gaps, poor planning, unrealistic timelines and rising construction costs as factors that can contribute to delayed housing delivery.
Source: Nairametrics